1.

The ‘Lifting Operations and Lifting Equipment Regulations 1998’ are:

a)

Legally enforceable under U.K Legislation

b)

Examples of good practice which may be followed by Lifting Contractors

c)

Recommendations from the Health and Safety Executive

d)

Guidance regulations produced by the Offshore Industry

2.

The main purpose of ‘LOLER 98’ is to:

a)

Inform employers about their responsibilities under the Health and Safety at Work Act

b)

Reduce the risk to a person’s safety due to the use of lifting equipment provided for work purposes

c)

Give information to lifting operators on the technical specification of lifting equipment

d)

Provide the lifting team with a time-frame for the operation

3.

It is the duty of every employer under the provisions of ‘LOLER 98’ to ensure that every operation involving lifting equipment is:

a)

Carried out with the minimum of disruption to normal operations

b)

Implemented safely, so far as is reasonably practicable having due regard to cost.

c)

Properly planned, supervised and carried out in a safe manner

d)

Completed within the time period stated in the lift plan

4.

It is the duty of every employer under the provisions of ‘LOLER 98’ to ensure that equipment exposed to conditions causing its deterioration, used for lifting persons is, unless subjected to a written scheme of thorough examination, thoroughly examined at least every:

a)

3 months

b)

6 months

c)

12 months

d)

24 months

5.

It is the duty of every employer under the provisions of ‘LOLER 98’ to ensure that the planning of lifting operations using lifting equipment is carried out by:

a)

The lifting operations team leader

b)

A competent person

c)

The crane operator

d)

An experienced person

6.

Lifting equipment must have sufficient strength and stability in order to ensure that:

a)

It is capable of lifting any load in any conditions

b)

It may be used in a range of applications and weather conditions

c)

It does not structurally fail when lifting a load within its design capabilities

d)

It is not limited to operations within its Safe Working Load (SWL)

7.

When dealing with lifting operations and lifting equipment in the offshore environment, the main regulatory document is the:

a)

Factories Act 1961

b)

Statutory instrument 1976 No 1019 (SI1019)

c)

Construction (Lifting Operations )Regulations 1961

d)

Lifting Operations and Lifting Equipment Regulations 1998 No SI 2307

8.

The purpose of PUWER legislation is to:

a)

Record and control working hours

b)

Control hazardous substances

c)

Regulate the use of work equipment

d)

Report all accidents and incidents

9.

The initials LOLER stand for:

a)

Lifting Operations Licensed Environment Regulations

b)

Lifting Operations and Lifting Equipment Regulations

c)

Licensed Operation Legal Equipment Requirements

d)

Limited Operations Lifting Environment Requirements

10.

The main Act dealing with Health and Safety in a UK workplace is the:

a)

VDU Screen Regulations

b)

Offices, Shops and Railways Act

c)

Factories Act

d)

Health and Safety at Work Act

11.

The main reason for ensuring that lifting operations are carried out in a proper and planned manner is to:

a)

Reduce the likelihood of delays due to unforeseen circumstances

b)

Ensure that the lift is carried out with minimum disruption to normal operations

c)

Minimise the risk of danger to persons

d)

Avoid additional costs which were not anticipated

12.

When carrying out a lifting operation, the risk of damage to the load being lifted or to structural components within the surrounding area will be reduced by:

a)

Proper planning, supervision and implementation of the lift by competent persons

b)

Providing all members of the lifting team with a copy of the lift plan

c)

Ensuring the lifting team have read the ‘LOLER 98’ document

d)

Having the lift plan checked by the crane operator

13.

The main purpose of lift planning is to ensure that:

a)

The lift is carried out with minimum disruption and expense

b)

Only experienced personnel are involved in the lifting operation

c)

A record is kept of all lifting operations

d)

The equipment provided is suitable for the task and the lift is carried out safely

14.

The prime purpose of a risk assessment for a lifting operation is to ensure that:

a)

A record is provided to show that steps have been taken to conform to health and safety legislation

b)

Hazards associated with the lifting operation are identified, their risks assessed and control measures implemented

c)

All equipment to be used in a specific lifting operation is available within the stores area and may be withdrawn at any time

d)

Lifting equipment is properly maintained and is stored in such a manner and environment that will not result in its deterioration.

15.

Statistics collated by the Health and Safety Executive show that accidents involving lifting activities are often related to:

a)

Use of equipment which has been incorrectly colour coded

b)

Hand held communication equipment interference

c)

Poor recording of lifting equipment inspections

d)

Lack of competence and effective planning

16.

According to research by the Health and Safety Executive:

a)

Lifting related activities are a significant cause of injuries to workers in the offshore industry.

b)

Lifting related activities are not a significant cause of injuries to offshore workers.

c)

The consequences of lifting related accidents are often minor.

d)

Lifting accidents happen frequently even where there is good supervision, effective lift plans are in place and operators are competent.

17.

Choose THREE correct options from the list provided To minimise the risk of injury to personnel due to structural obstructions along the route of a lift:

a)

The lifting team must be coordinated by the slinger

b)

The lifting team must be comprised of competent personnel

c)

The lifting plan must take account of the obstructions

d)

The lifting operation must be carried out in a safe and controlled manner

e)

The lifting operation must be carried out during daylight hours

18.

A ‘safe system of work’ is required:

a)

When an operative is working alone

b)

During any work operation

c)

When more than 5 people are involved in the activity

d)

During a task which requires the use of Personal Protective Equipment

19.

The purpose of a toolbox talk is to:

a)

Confirm sufficient tools for the work to be done are in good working order

b)

Confirm that tools are withdrawn from stores and returned properly

c)

Familiarise the workforce with the tools to be used and how they are operated

d)

Discuss the scope the of work and raise awareness of any factors that could affect safety while working.

20.

In relation to lifting operations, a ‘hazard’ may be described as:

a)

A condition in which an item of equipment is deemed unsuitable for a specific lifting operation.

b)

Any item of lifting equipment which has not undergone a pre-use inspection and has not been correctly colour coded

c)

Any situation having the potential to cause harm to the health and safety of personnel or damage to property, plant or the environment

d)

A lifting operation which has not been risk assessed and for which no lift plan has been produced

21.

When a routine lifting operation is repeated regularly the lifting team must ensure that they:

a)

Do not become complacent with the operation

b)

Do not familiarise themselves with the lifting plan

c)

Commit the lifting plan to memory

d)

Use a range of techniques to relieve the boredom of routine

22.

The practice of trying to physically control a load as it is landed should be avoided since this could lead to the:

a)

Load being damaged

b)

Misalignment of lifting gear

c)

Load being landed in the wrong place

d)

Entrapment of limbs or fingers

23.

Where there is a likelihood that persons could be injured by a shifting or falling load during a lifting operation they should:

a)

Not enter the danger area until the lifting operation is complete.

b)

Be accompanied at all times by a competent lifting operator

c)

Wear appropriate personal protective equipment including a high visibility jacket

d)

Inform the crane operator of their presence in the danger area

24.

When two lifting operations are being carried out at the same time, they:

a)

May use the same lifting team

b)

Must utilise the same lifting appliance

25.

When two lifting operations are being carried out at the same time, they:

a)

May use the same lifting team

b)

Must utilise the same lifting appliance

c)

Must not result in conflicting crane operations

d)

May use the same risk assessment

26.

During adverse weather conditions, lifting operations must be:

a)

Allowed to continue as normal

b)

Limited in relation to the severity of the conditions

c)

Allowed to continue as normal but with increased supervision

d)

Completed as quickly as possible

27.

Identify the conditions which are considered as hazards during a lifting operation:

a)

Good communications between team members

b)

Unauthorised personnel in the lifting area

c)

The use of competent personnel

d)

Obstructions along the lift route

e)

The potential for a load to be dropped

28.

It is safe to use a damaged lifting accessory provided that:

a)

The competent person has been informed

b)

It is never safe to use damaged lifting accessories

c)

The damage is minor and relates only to the attachment point

d)

The last inspection was carried out less than one week previously

29.

Lifting personnel should not stand under a load during a lifting operation since:

a)

Their line of sight to the crane operator would be obscured

b)

The Banksman would not be able to communicate effectively with the crane operator

c)

The load or some other object might drop causing them injury

d)

This would invalidate the lifting plan

30.

If the Safe Working Load (SWL) marked on an item of lifting equipment cannot be clearly read then that item:

a)

Should not be used without prior permission of the supervisor

b)

Should be used only for small loads

c)

Should be used with great care

d)

Should not be used under any circumstance

31.

A lack of maintenance or regular inspection of lifting equipment could result in:

a)

A reduction in the Safe Working Load (SWL) of the lifting device

b)

An increased likelihood of the load falling due to failure in load bearing components

c)

A need to replace Personal Protective Equipment more frequently in case of premature failure

d)

No significant increase in the level of hazard or risk to personnel involved in lifting operations

32.

When conducting a lifting operation, the Banksman is identified by:

a)

Waving to the crane operator

b)

Wearing high-visibility reflective clothing

c)

Wearing a radio communications set

d)

Informing the crane operator at the start of the shift

33.

If a task involving lifting operations has no associated risk assessment you should:

a)

Carry out the task taking particular care

b)

Have a tool-box talk about the task

c)

Not start the task

d)

Carry out a risk assessment after the task is completed

34.

When undertaking lifting operations, hazards which must be considered include:

a)

Working at heights

b)

The non-attendance of the Safety Representative

c)

Crane operation by a competent person

d)

Working close to ‘live’ equipment

e)

The possibility of toxic material spillage

35.

In order to minimize risk during a rigging operation, personnel should have adequate:

a)

Refreshments

b)

Access space

c)

Working space

d)

Comfort breaks

e)

Lighting

36.

The main duties of a Rigger are:

a)

Acting as the Health and Safety representative for the lifting team

b)

Coordinating the lifting team members during the operation

c)

Attaching, detaching and securing loads to lifting equipment during a lifting operation

d)

Providing manoeuvring signals to the crane operator

37.

The person responsible for communicating manoeuvring signals to the crane operator during a lifting operation is the:

a)

Rigger

b)

Banksman

c)

Supervisor

d)

Load Handler

38.

A crane may only be operated by:

a)

An experienced Banksman

b)

The Deck Foreman

c)

The OIM

d)

A competent Crane Operator

39.

The duties of a Banksman include:

a)

Supervising the lifting operation

b)

Tidying the work area on completion of the lifting operation

c)

Communicating with the lifting team

40.

Choose THREE correct options from the list provided: The duties of a Banksman include:

a)

Supervising the lifting operation

b)

Tidying the work area on completion of the lifting operation

c)

Communicating with the crane operator using hand signals or hand-held radio

d)

Ensuring the lifting operation is carried out safely

e)

Erecting and removing barriers as required

41.

It is required under the provision of ‘LOLER 98’ that lifting equipment is of adequate:

a)

Strength and stability for the relevant load

b)

Size and suitability for the lifting operation

c)

Rating and reliability for a given lift

d)

Capability and capacity for its intended use

42.

Unless subjected to a written scheme of examination, lifting accessories must be thoroughly examined by a competent person, at intervals not exceeding:

a)

2 months

b)

6 months

c)

1 year

d)

2 years

43.

As the user of lifting equipment and lifting accessories you should inspect them:

a)

Every week

b)

Every month

c)

Every 6 months

d)

Each time before and after use

44.

A lifting accessory is:

a)

another name for lifting machine

b)

an item used to attach the lifting machine to supporting steelwork

c)

an item connecting the lifting machine to the load

d)

an item used to secure a load onto a pallet

45.

Choose THREE correct options from the list provided: The planning of lifting operations is required in order to:

a)

Comply with the requirements of ‘LOLER 98’

b)

Set out detailed instructions on how the lift should be carried out

c)

Provide a cost analysis of the lifting operation

d)

Identify the equipment required to carryout the lift

e)

Evaluate the competency of the lifting team

46.

The preparation of a lifting plan must be carried out by a:

a)

Trainee under supervision

b)

Banksman

c)

Crane operator

d)

Competent person

47.

Choose THREE correct options from the list provided: A lifting plan should include:

a)

Reference to a relevant risk assessment

b)

Details of load and equipment to be used

c)

A copy of the most recent crane inspection report

d)

Details of the lifting route to be used and the set down position

e)

A list of qualified first aid personnel

48.

Choose THREE correct options from the list provided: A properly constructed lifting plan will:

a)

Comply with the requirements of ‘LOLER 98’

b)

identify the equipment to be used

c)

Ensure equipment is regularly inspected

d)

Detail the steps involved in undertaking the lifting operation

e)

Specify the PPE to be worn by the lifting team

49.

Choose FOUR correct options from the list provided: When planning a lift you must know the:

a)

Correct equipment

b)

Path of load travel

c)

Weight of the load

d)

Configuration of the load

e)

Time of day

50.

When using a sling during an operation to lift a load having sharp edges, appropriate packing should be used to:

a)

Minimise damage to the sling and the load

b)

Ensure that the load is held more securely during the lifting operation

c)

Provide for easier handling

d)

Provide suitable points for the attachment of tag lines

51.

Choose THREE correct options from the list provided: Where more than one collar eyebolt is fitted to a load for lifting purposes they should:

a)

All have the same Safe Working Load (SWL) rating

b)

Have the sling reeved through the eyebolts

c)

Be correctly aligned with the lifting point

d)

Be attached directly to the lifting hook

e)

Have an adequate Safe Working Load (SWL) rating for the load

52.

If you are required to use a shackle during a lifting operation and find that its pin is missing, you should:

a)

Replace the pin with a screwed bolt of the correct length and diameter

b)

Replace the pin with a machined screw which fits the shackle attachment

c)

Obtain a replacement shackle

d)

Obtain a bolt threaded along its entire length

53.

A shackle is used to:

a)

Provide a lifting point on a load

b)

Lift long or awkward shaped loads

c)

Provide a connection point for tag lines

d)

Link lifting accessories together

54.

When using multi-leg slings, the angle between the legs should be in the range:

a)

10° and 60°

b)

20° and 80°

c)

30° and 90°

d)

45° and 120°

55.

A vertical plate clamp may be used to:

a)

Lift a plate vertically

b)

Turn a plate from horizontal to vertical

c)

Suspend Loads

d)

Lift more than one plate in a single lift

56.

A vertical plate clamp should not be used to lift loads of less than:

a)

20 % of rated jaw capacity

b)

40 % of rated jaw capacity

c)

50% of the lifting appliance rated capacity

d)

30 % of lifting appliance rated capacity

57.

When selecting a sling for a lifting operation the most important factor to consider is the:

a)

Number of lifts required

b)

Weight of the load

c)

Time between lifts

d)

Number of personnel required

58.

When is it permissible to bundle different lengths of scaffold tubulars together in the same bundle for lifting purposes?

a)

If prior permission is obtained from the supervisor

b)

Provided the entire length of every tubular is contained within the span of the slings

c)

Irrespective of tubular length

d)

If the crane operator has visual contact with the load at all times

59.

When is it permissible to bundle different diameters of drilling tubulars together in the same bundle for lifting purposes?

a)

If prior permission is obtained from the supervisor

b)

Under no circumstances whatever

c)

Provided the Banksman is satisfied that the bundle can be safely lifted

d)

If the crane operator has visual contact with the load at all times

60.

When linking THREE lifting accessories together in one shackle, you should use a:

a)

Dee shackle

b)

Bow shackle

c)

Joggle shackle

d)

Lugged joining shackle

61.

If a wire rope has been ‘bird caged’, this would be due to it having been:

a)

Crushed

b)

Shock loaded

c)

Lubricated

d)

Spliced

62.

‘Spread’ or ‘Stretch’ of a lifting hook may be caused by:

a)

Corrosion

b)

Back hooking

c)

The use of a shackle

d)

Overloading

63.

The initials WLL stand for:

a)

Working Load Limit

b)

Wide Lifting Load

c)

Working Lift Limitation

d)

Widest Loading Lift

64.

The initials SWL stand for:

a)

Site Working Limit

b)

Safe Working Load

c)

Secure Wide Load

d)

Standby Working Limitation

65.

Choose THREE correct options from the list provided When slinging a load the angle between slings is found to be greater than 120°. Alternative methods of lifting the load would include using:

a)

Shorter slings

b)

Longer strops or chains

c)

An additional shackle

d)

A spreader beam

e)

A lifting frame

66.

The SWL of a fibre sling when using the choked lifting mode will:

a)

Remain unchanged

b)

Increase by 2%

c)

Double

d)

Reduce by 20%

67.

When slinging tubulars, the percentage distance from either end at which the slings should be positioned is:

a)

10%

b)

15%

c)

25%

d)

30%

68.

If the snatch block attached to a derrick crown is used to winch a weight of 2 Tonnes, the minimum SWL of the head fitting on the snatch block should be:

a)

2 Tonnes

b)

3 Tonnes

c)

4 Tonnes

d)

5 Tonnes

69.

When slinging a load using the choked method the choke angle should be:

a)

75°

b)

80°

c)

90°

d)

120°

70.

If two slings are used at an angle of approximately 90° to lift a 10 tonne weight, the approximate tension in each leg will be:

a)

5 tonne

b)

6 tonne

c)

7 tonne

d)

10 tonne

71.

The maximum recommended angle at which multi-leg slings should be used is:

a)

30°

b)

60°

c)

90°

d)

120°

72.

Any device which is used, or designed to be used, directly or indirectly, to connect a load to a lifting appliance and does not form part of the load, is known as a:

a)

Lifting component

b)

Lifting accessory

c)

Lifting item

d)

Lifting element

73.

An item of lifting equipment is defined as:

a)

An item used to attach a load to a lifting device

b)

A device having the ability to secure a load during a lifting operation

c)

A mechanical device capable of raising or lowering a load

d)

An item used to control the lifting operation

74.

Choose FOUR correct options from the list provided Identify the lifting accessories from the following:

a)

Crane Pennant

b)

Slings

c)

Eyebolt

d)

Crane

e)

Shackle

75.

Choose FOUR correct options from the list provided Identify the lifting equipment from the following:

a)

Winch

b)

Hoist

c)

Slings

d)

Crane

e)

Chain Block

76.

Match the lifting accessories shown in List (a) with the description shown in List (b)

4 lines
77.

Choose TWO correct options from the list provided: The main types of pin used in shackles are:

a)

Rolling pin

b)

Screw pin

c)

Safety pin

d)

Ten pin

78.

The most common type of eyebolt used offshore is the:

a)

Screwed shank

b)

Collar

c)

Collarless

d)

Dynamo

79.

Tirfors can only be used with:

a)

Dyform wire rope

b)

Maxiflex wire rope

c)

Fuse wire rope

d)

General purpose wire rope

80.

When released, the control lever on an air winch should return to the:

a)

Lower position

b)

Reverse position

c)

Neutral position

d)

Hoisting position

81.

The force applied to the hand chain block should require:

a)

sufficient persons to move the load

b)

One-handed operation only

c)

A mechanical aide

d)

One-man operation only

82.

Whilst operating a Tirfor you should never:

a)

Lift a load

b)

Operate under water

c)

Operate both handles at once

d)

Pull a load

83.

The type of beam clamp suitable for longitudinal side loading is the:

a)

King clamp

b)

Universal super clamp

c)

Multi-purpose clamp

d)

Jet clamp

84.

When a winch wire rope and hook are at their lowest point, the recommended number of full rope turns left on the drum must not be less than:

a)

One

b)

Five

c)

Six

d)

Ten

85.

A standard beam clamp should be used for:

a)

Vertical lifts only

b)

Lifts at any angle

c)

Horizontal movement of loads

d)

Multifunctional lifts

86.

A beam trolley is used in conjunction with a runway beam to provide a:

a)

Point at which to anchor a clamp

b)

Fixed lifting position

c)

Support and traversing function

d)

Reference point during a blind lift

87.

If the pawl release mechanism on a manually-operated chain hoist is disengaged while a load is being lifted, the load will:

a)

Be raised

b)

Lock in position

c)

Be lowered slowly

d)

Drop quickly

88.

A manually operated chain hoist is designed to be operated:

a)

With the aid of an extension handle

b)

As a two-man device

c)

By one man only

d)

With additional gearing if required

89.

The lifting and lowering functions of a chain block are carried out by means of:

a)

An endless hand chain

b)

A motorised chain mechanism

c)

An operating lever

d)

A geared handle