Risk response Strategies (Positive) - Assignment

Quiz
•
Professional Development
•
Professional Development
•
Medium
Afghanistan Center
Used 2+ times
FREE Resource
7 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Nangarhar province, the project team discovers that a supplier can provide high-capacity equipment that would finish work two weeks ahead of schedule. The PM adjusts the plan and secures the supplier immediately. What strategy is being used?
Exploit
Enhance
Accept
Share
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Herat province, the team has a chance to finish ahead of schedule if additional skilled resources are brought in. The PM assigns extra personnel to improve the likelihood of early completion. What response strategy is this?
Enhance
Accept
Share
Escalate
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project in Kabul could gain wider adoption if a software feature is co-developed with an external startup. The PM proposes a formal partnership with the startup to develop the feature together. Which strategy is being applied?
Share
Enhance
Accept
Escalate
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Samangan province, weather conditions may allow faster deliveries, but the team decides not to change plans. They’ll benefit from the faster delivery only if it occurs naturally. Which strategy does this describe?
Accept
Enhance
Share
Exploit
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Delhi, a new government grant could benefit the organization. Since it affects the overall business and not just the project, the PM informs the program management office. What strategy is this?
Escalate
Share
Accept
Enhance
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Balkh province, a skilled team member suggests a faster method that could reduce delivery time. The PM provides extra tools to help the team implement the method. What strategy is being used?
Enhance
Exploit
Share
Accept
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project in Panjshir province could attract media attention and raise visibility. The PM partners with a local NGO to jointly share and promote the project’s success. Which strategy is being used?
Share
Escalate
Accept
Exploit
Similar Resources on Wayground
10 questions
COMMON QUESTION WB 0513 QUIZ

Quiz
•
Professional Development
7 questions
Risk Response Strategies (Negative) - Assignment

Quiz
•
Professional Development
7 questions
Final Quiz - Assignement

Quiz
•
Professional Development
7 questions
Integration Process - Assignment

Quiz
•
Professional Development
7 questions
Conflict Resolution Techniques - Assignment

Quiz
•
Professional Development
8 questions
Disposition Quiz #2- Day 3

Quiz
•
Professional Development
10 questions
Assessment & Evaluation

Quiz
•
Professional Development
10 questions
Halloween Candy Trivia Challenge

Quiz
•
Professional Development
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade